A forecast is a chain of assumptions about wells, facilities and downtime. Making each link visible is what turns a number into a tool for decisions.
The situation
Production forecasts combine reservoir deliverability, well and facility constraints, planned and unplanned downtime, and ramp-up assumptions. Probabilistic forecasting (P90/P50/P10) communicates uncertainty better than a single number.
Forecasts often fail because one assumption is optimistic and hidden inside the total: new wells arriving on time, a shutdown taking the planned days, or a facility running at full capacity all year.
Present low, mid and high cases with the main drivers of each. Decision makers need to know what could move the number and by how much.
Compare forecast against actual each month by layer. Where the gap is consistent, fix the assumption rather than the total.
Good forecasts support budgets, export nominations, staffing and maintenance planning. Share the assumptions with each of these users.
We review production forecasts, reconcile them with actual performance and help integrate forecasting with activity planning.
A forecast assumed 97% facility availability with no ramp-up period. Actual first-year availability was in the high 80s. The plan's revenue fell short and the gap had to be explained to partners.
Decline curve analysis on early data over-predicted plateau length. Compression was installed two years later than needed, so production fell below contract delivery volumes.
Links go to the publisher's official page (ISO, IEC, BSI, API, NFPA, HSE and others). Most standards must be bought from the publisher.
Take this briefing with you
A one-to-two page PDF summary: situation, diagram, key takeaways, consequences, examples and standards.